This exercise begins with a list of tasks for a wedding project. Working in Microsoft Project, you will create the task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors, add resources, and make changes to the original plan. Enter the following tasks, including the specified duration, specified predecessors, and specified resources. Tasks that are bolded are summary tasks and the indented tasks are sub-tasks.

Enter the following list of resources into the same Microsoft Project file that you entered the above task list.

Change the Project from being scheduled from a Start date, to being scheduled from a Finish Date. The Finish Date is the date of the wedding, November 12th, 2015.

Change the constraints on the following Tasks:

- Task Constraint Update list of Guests Attending Finish no later than November 10, 2015

- Final Fitting Finish no later than November 6, 2015

- Schedule Rehearsal Dinner Must start on November 11, 2015

- Apply for Wedding License Finish no later than November 10, 2015

Finally, submit your finished homework assignment to Canvas. Saving/Naming Your File: When you save your file make sure that your name and the project number are included in it.

Paper For Above instruction

The successful planning and execution of a wedding involves meticulous organization and effective project management. Microsoft Project is a powerful tool that facilitates the detailed scheduling, resource allocation, and constraint management necessary for such complex events. This paper outlines the process of developing a wedding project plan using Microsoft Project, emphasizing task creation, resource assignment, schedule adjustments, and constraint modifications to ensure timely completion of all wedding-related activities.

To initiate the plan, a comprehensive list of tasks must be established. These tasks typically include major milestones such as booking the venue, sending invitations, selecting and fitting the wedding dress, and obtaining the marriage license. In this particular project, tasks are categorized as summary tasks and sub-tasks. Summary tasks group related activities for clarity and easier management, while sub-tasks detail the specific actions needed within each category. For example, "Final Preparations" can be a summary task with sub-tasks like final dress fitting, arranging transportation, and final guest count confirmation. Properly indenting these sub-tasks under their respective summary tasks in Microsoft Project creates a hierarchical structure that reflects the dependencies and flow of activities.

Resource allocation is a critical component in wedding project management. Resources include personnel such as the bride, groom, wedding planner, dressmaker, and vendors, as well as physical resources like venues, decorations, and transportation. Properly entering resources into Microsoft Project allows for effective tracking of their availability and workload. Assigning resources to specific tasks ensures accountability and helps prevent overbooking, which is crucial for smooth execution as wedding dates approach.

Another important aspect involves setting the project's scheduling parameters. Initially, the project schedule might be based on a start date; however, setting the schedule to be driven from a fixed finish date offers more control, especially when the wedding date is non-negotiable. In this case, the finish date is set for November 12th, 2015. Transitioning to a finish-date driven schedule in Microsoft Project can be achieved through the project settings, allowing the planner to determine backward scheduling of tasks to meet the final deadline. This approach ensures that all activities are completed in time for the wedding, considering their durations and dependencies.

Constraints on specific tasks significantly influence the project timeline. Adjusting these constraints allows project managers to ensure key activities occur within necessary timeframes. For example, updating the "list of Guests Attending" to finish no later than November 10th is essential so that final guest counts can be confirmed ahead of the wedding. Likewise, "Final Fitting" should be constrained to finish by November 6th to allow adequate time for alterations. The "Rehearsal Dinner" must be scheduled to start precisely on November 11th, ensuring the wedding rehearsal proceeds as planned. Additionally, "Applying for Wedding License" must be completed no later than November 10th to meet legal requirements, avoiding last-minute complications.

Throughout this process, it is vital to regularly review and adjust the plan. Modifications to constraints, durations, and resources may be necessary as circumstances change. Saving the project file with appropriate naming conventions, including the planner's name and project number, ensures proper documentation and easy reference. Once complete, the finalized project schedule provides a clear roadmap for executing the wedding, minimizing risks of delays or oversights, and facilitating efficient communication among all stakeholders.

References

  • Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Wiley.
  • Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). PMI.
  • Larson, E. W., & Gray, C. F. (2018). Project Management: The Managerial Process. McGraw-Hill Education.
  • Heldman, K. (2018). PMP Project Management Professional Exam Study Guide. Wiley.
  • Schwalbe, K. (2018). Information Technology Project Management. Cengage Learning.
  • Heagney, J. (2016). Fundamentals of Project Management. AMACOM.
  • Meredith, J. R., & Mantel, S. J. (2017). Project Management: A Managerial Approach. Wiley.
  • Lock, D. (2017). Project Management. Gower Publishing.
  • IPMA. (2006). Competence Baseline (ICB 3). International Project Management Association.
  • Wysocki, R. K. (2014). Effective Project Management: Traditional, Agile, Extreme. Wiley.