Based On The Project Requirements Document You Created
Based On The Project Requirements Document You Created From Week Two
Based on the Project Requirements Document you created from Week Two, create one detailed project plan in a work breakdown structure (WBS) format that presents at least five major activities and at least three tasks per major activity. The detailed WBS should be in tabular format, including columns for activity name, task name, percent completion, start date, finish date, resource, number of days duration, and precedent task. Populate the table with data, using real or imaginary information, ensuring that dates and precedent tasks are logically consistent. Additionally, create a Logical Precedence Diagramming Method (PDM) network diagram based on the WBS, illustrating at least one series, one parallel, one start-to-start, and one finish-to-finish relationship. The diagram should use boxes, arrows, task numbers, and clearly demonstrate the relationships between tasks. The submission should be in Microsoft Word or Excel and cover a minimum of one page each.
Paper For Above instruction
Developing a Comprehensive Project Plan and PDM Network Diagram Based on Week Two Requirements
Effective project management relies heavily on meticulous planning, where a work breakdown structure (WBS) clearly delineates the project activities and tasks, and a precedence diagram visualizes the sequence and relationships among these tasks. This paper explores the creation of a detailed project plan in WBS format, and a subsequent PDM network diagram, based on the project requirements developed in Week Two.
Constructing the Work Breakdown Structure (WBS)
The WBS serves as the backbone of project planning, breaking down the project into five major activities, each encompassing three specific tasks. For illustration, consider a project aimed at developing a new software application. The five major activities could include Requirement Analysis, Design, Development, Testing, and Deployment. Each activity encompasses specific tasks, with assigned resources, durations, start and finish dates, and logical dependencies ensuring coherency.
For Requirement Analysis, tasks might include stakeholder interviews, requirement documentation, and approval processes. Design could involve UI design, system architecture planning, and prototype development. Development might comprise coding modules, integration, and initial review. Testing could include unit testing, system testing, and user acceptance testing. Deployment involves environment setup, data migration, and final deployment. Each task is assigned a realistic start and end date, with precedence reflecting their logical sequence. For instance, requirement documentation must precede approval, coding must follow system architecture planning, and testing follows development completion.
Populating the Table with Data
The activities and tasks are populated with sample data. For example, stakeholder interviews might start on 01/02/2024 and conclude by 01/05/2024, with a resource assigned as Business Analyst, and 4 days duration. Coding modules could start on 02/15/2024, lasting 10 days, with a developer as the resource. Percent complete estimates inform progress tracking, starting at 0% for initial planning stages. The inclusive approach ensures the logical flow and practical scheduling of project activities.
Creating the PDM Network Diagram
Building the PDM diagram involves translating the WBS into a visual sequence with boxes (tasks), arrows (relationships), and labeled task numbers. A series relationship, such as requirement analysis preceding design, is illustrated with a directed arrow. Parallel relationships, such as simultaneous coding and testing phases, are depicted with concurrent task boxes branching from a common start point. Start-to-start relationships exemplify tasks that begin simultaneously, for example, system design and initial prototype development. Finish-to-finish relationships show tasks that conclude together, like system testing and bug fixing.
The diagram aims to depict the logical flow, dependencies, and concurrency inherent in project execution, facilitating better planning and control. Using software like Microsoft Word or Excel, the diagram spans at least one page, incorporating clear labels and visual clarity to aid comprehension.
Conclusion
Creating a comprehensive WBS and an associated PDM network diagram is essential for effective project management. The structured breakdown ensures clarity of activities and tasks, while the network diagram provides a visual map of task relationships and sequences. Together, these tools enable project managers to anticipate dependencies, allocate resources efficiently, and monitor progress systematically, ultimately leading to successful project delivery.
References
- Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Wiley.
- PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 6th Edition. Project Management Institute.
- Schwalbe, K. (2015). Information Technology Project Management. Cengage Learning.
- Heldman, K. (2018). Project Management JumpStart. Wiley.
- Gido, J., & Clements, J. (2018). Successful Project Management. Cengage Learning.
- Verzuh, E. (2015). The Fast Forward MBA in Project Management. Wiley.
- Leach, L. P. (1999). Critical Chain Project Management. Artech House.
- Larson, E., & Gray, C. (2018). Project Management: The Managerial Process. McGraw-Hill Education.
- Milosevic, D., & Patanakul, P. (2016). Project Management: A Systems Approach. CRC Press.
- Ralph L. Kliem, & Rodney L. Montag. (2010). Effective Project Management. ASQ Quality Press.