Beck Company Beck Manufacturing Al Beck, president of Beck Manufacturing, wants to determine the capacity of his facility, which produces steering gears for auto manufacturers. The company operates a product layout that involves sequential operations including milling, grinding, boring, drilling, and assembling, to produce nearly identical products in large quantities. To effectively plan for capacity and future expansion, it is essential to analyze the capacity constraints of each operation and identify potential improvements.
The manufacturing process comprises multiple machine centers with differing numbers of machines and processing times per piece. The milling operation has five machines, each requiring two minutes per part; grinding involves seven machines, processing each part in three minutes; boring includes three machines with one-minute processing per piece; and drilling involves the use of a single machine with a half-minute per product. Assembly, though not constrained by machine availability, is flexible and can be scaled to meet increased demand.
The production takes place over two 8-hour shifts daily, totaling 16 hours of operation, with an additional third shift reserved for maintenance. This results in a total of 48 hours per day available for production activities. When calculating capacity, it is crucial to convert this available time into the number of units each operation can produce, based on machine processing times and capacities. For example, the capacity of the milling operation can be computed by dividing total available machine time by the processing time per part, adjusting for the number of machines. Specifically, for milling, each machine operates 16 hours per day; thus, the total available machine hours per day is 16 hours multiplied by five machines, which equals 80 machine-hours. Since each part requires two minutes (or 1/30 hours) to mill, the total units produced per day on the milling line is 80 hours divided by (1/30), equaling 2,400 units. Similar calculations for grinding, boring, and drilling reveal their respective capacities and highlight the bottleneck process.
Grinding, with seven machines each processing in three minutes per part, has a capacity of (16 hours 7 machines) divided by (3 minutes / 60), resulting in a maximum of 1,120 units per day. Boring, with three machines and a one-minute processing time, can produce 16 hours 3 machines divided by 1 minute, equating to 2,880 units daily. Drilling, with a single machine and a half-minute processing time, can produce up to 16 hours divided by 0.5 minutes, which equals 1,920 units per day. Comparing these capacities indicates that grinding is the most significant limiting factor, as it provides the lowest maximum output rate, making it the system’s bottleneck.
The overall capacity of the system is dictated by this bottleneck; therefore, the system’s maximum production capacity is approximately 1,120 units per day. To increase capacity, Beck could focus efforts on alleviating bottlenecks, primarily by adding more grinding machines or improving grinding efficiency. Since assembly modifications are straightforward and flexible, increasing assembly line capacity could also be advantageous, assuming upstream processes are adequately scaled to supply assembly with parts.
Expanding capacity without acquiring new equipment necessitates a strategic approach. One possibility involves optimizing existing machine utilization through process improvements, such as reducing machine downtime via preventive maintenance or process improvements that decrease cycle times. Lean manufacturing principles could be applied to eliminate waste and enhance workflow efficiencies across the shop floor. Additionally, implementing overtime during current machine operation hours could temporarily elevate capacity until permanent solutions are instituted. Cross-training employees to operate multiple machines may also help optimize machine utilization and reduce idle time in non-bottleneck areas.
Furthermore, rearranging the production schedule to balance workloads across different operations can help maximize existing capacity. These measures, together with targeted investments in process improvements and workforce development, offer a pathway for capacity expansion without significant capital expenditure.
In conclusion, the capacity of Beck Manufacturing’s facility hinges largely on the grinding operation, which restricts the overall output. To support future growth, the company should prioritize increasing grinding capacity, optimizing current processes, and implementing lean principles to improve efficiency. Such strategies will enable Beck Company to meet growing demand effectively and sustain competitive advantage within the automotive parts manufacturing industry.
Paper For Above instruction
Beck Company, under the leadership of President Al Beck, seeks to understand and optimize its manufacturing capacity for steering gears. The facility operates with a sequence of operations—milling, grinding, boring, drilling, and assembly—each essential to producing nearly identical products efficiently. As a product layout, this process demands precise capacity calculations at each stage to determine bottlenecks and opportunities for expansion. Analyzing process times, machine availability, and operational schedules reveal critical insights into capacity constraints and guide strategic decision-making for future growth.
The core of capacity analysis involves quantifying the maximum output each operation can achieve within the available working hours. The plant operates two 8-hour shifts daily, supplemented by a third shift for maintenance, summing up to 48 hours of operational time per day. For milling, with five machines each requiring two minutes per part, total machine-hours per day amount to 80 hours (5 machines * 16 hours). Dividing this by the 2-minute processing time (converted to hours as 1/30 hour) provides a capacity of 2,400 units per day for the milling operation.
Similarly, the grinding operation, with seven machines and a processing time of three minutes per piece, has a total available machine-hours of 112 hours (7 machines 16 hours). The capacity for grinding is thus approximately 1,120 units per day (112 hours / 0.05 hours per unit). Boring, with three machines at a one-minute cycle time, results in a capacity of 2,880 units (48 hours 3 machines / 1 minute). Drilling, with one machine requiring 0.5 minutes per product, can produce 1,920 units per day (48 hours / 0.5 minutes).
Comparing these capacities highlights that the grinding stage is the bottleneck, with the lowest maximum capacity of 1,120 units per day. Since the entire manufacturing process is constrained by this stage, the overall system’s capacity mirrors this figure. Addressing this bottleneck is critical for capacity expansion. Potential solutions include increasing the number of grinding machines or improving grinding efficiency through process enhancements.
Expanding capacity without new equipment involves process and operational improvements. Implementing lean manufacturing principles can streamline workflows, minimize downtime, and enhance efficiency across operations. For instance, preventive maintenance and process optimization can reduce machine idling. Workforce flexibility, such as cross-training employees to operate multiple machines, can also improve utilization. Scheduling adjustments, like staggered shifts or overtime, can temporarily boost output without capital costs. Additionally, better planning and scheduling ensure balanced workloads across all operations, preventing idle times and maximizing existing resources.
Investment in employee training to foster multi-skilled operators is another tactic that can lead to increased throughput without acquiring new machinery. These approaches—focused on enhancing existing capacity—are sustainable strategies that align with lean principles, improve workflow, and reduce waste. They are integral to capacity planning and operational excellence, allowing the company to meet rising demands efficiently.
In conclusion, the primary capacity constraint in Beck Manufacturing resides in the grinding operation, which limits overall output. Strategic efforts should focus on expanding grinding capacity through additional equipment or process improvements. Nevertheless, significant gains can be achieved through operational efficiencies, process optimization, workforce development, and effective scheduling. These measures collectively enable capacity growth without the immediate need for substantial capital investment, positioning Beck Company to sustain competitive advantage and meet increasing automotive industry demand.
References
- Heizer, J., Render, B., & Munson, C. (2020). Operations Management (13th ed.). Pearson.
- Slack, N., Brandon-Jones, A., & Burgess, N. (2019). Operations Management (9th ed.). Pearson.
- Krajewski, L., Malhotra, M. K., & Ritzman, L. P. (2020). Operations Management: Processes and Supply Chains (12th ed.). Pearson.
- Chase, R. B., Jacobs, F. R., & Aquilano, N. J. (2019). Operations Management for Competitive Advantage (12th ed.). McGraw-Hill.
- Glassock, D. (2018). Lean Manufacturing: A Practical Guide. Journal of Manufacturing Technology, 34(2), 56-65.