Determine The Schedule And Cost Variance For A Project

Determine The Schedule And Cost Variance For A P

Determine the schedule and cost variance for a project that has an actual cost at month 20 of $750,000, a scheduled cost of $600,000 and an earned value of $700,000.

Determine the schedule variance, cost variance, SPI, CPI, and CSI for a project that has an actual cost at month 12 of $90,000, a scheduled cost of $100,000 and an earned value of $120,000.

A software development project at day 60 exhibits an actual cost of $300,000 and a scheduled cost of $375,000. The software manager estimates a value completed of $300,000. Determine the schedule variance, cost variance, SPI, CPI, and time variance for the project.

A project to develop a county park has an actual cost in month 24 of $240,000, a planned cost of $290,000, and a value completed of $80,000. Determine the schedule variance, cost variance, SPI, CPI, and CSI for the project.

Paper For Above instruction

Project management is a critical discipline that encompasses the planning, executing, and controlling of projects to achieve specific objectives within constraints such as time, cost, and scope. One of the fundamental aspects of project management is monitoring project performance through variances and performance indices, which provide insights into project health and facilitate informed decision-making. This paper discusses the concepts of schedule variance (SV), cost variance (CV), schedule performance index (SPI), cost performance index (CPI), and cost schedule index (CSI), and demonstrates their calculation through multiple project scenarios.

Schedule and Cost Variance Calculations

Schedule variance (SV) and cost variance (CV) are essential metrics used to assess whether a project is on schedule and within budget, respectively. SV is calculated as the difference between the Earned Value (EV) and the Planned Value (PV), expressed as:

  • SV = EV - PV

Similarly, CV measures the cost efficiency of work performed and is calculated as:

  • CV = EV - Actual Cost (AC)

Applying these formulas to the first scenario where, at month 20, the project has an AC of $750,000, a PV of $600,000, and an EV of $700,000:

  • SV = 700,000 - 600,000 = $100,000
  • CV = 700,000 - 750,000 = -$50,000

A positive SV indicates the project is ahead of schedule, while a negative CV suggests it is over budget.

Performance Indices: SPI and CPI

The Schedule Performance Index (SPI) and Cost Performance Index (CPI) offer normalized measures of schedule and cost performance, ranging between 0 and 1 (or above 1 if performance exceeds expectations). They are calculated as:

  • SPI = EV / PV
  • CPI = EV / AC

For the second scenario, at month 12, the calculations are:

  • SPI = 120,000 / 100,000 = 1.2
  • CPI = 120,000 / 90,000 ≈ 1.33

SPI greater than 1 indicates the project is ahead of schedule, while a CPI above 1 shows cost efficiency.

Schedule and Cost Indices: CSI and Time Variance

The Cost Schedule Index (CSI) is sometimes used interchangeably with other metrics but often refers to a combined measure of schedule and cost performance. The Time Variance (TV) assesses deviations in project duration, calculated as:

  • Time Variance = Expected Duration - Actual Duration

Assuming the planned project duration, the third and fourth scenarios involve calculating these indices based on the provided values, which help project managers understand overall project health.

In the third scenario, at day 60, with an EV of $300,000, AC of $300,000, and PV of $375,000:

  • SV = 300,000 - 375,000 = -$75,000 (behind schedule)
  • CV = 300,000 - 300,000 = $0 (cost on budget)
  • SPI = 300,000 / 375,000 ≈ 0.8
  • CPI = 300,000 / 300,000 = 1.0

The lower SPI indicates a schedule delay, while CPI of 1 signifies cost efficiency.

In the fourth scenario, with an EV of $80,000, AC of $240,000, and PV of $290,000:

  • SV = 80,000 - 290,000 = -$210,000 (significant delay)
  • CV = 80,000 - 240,000 = -$160,000 (over budget)
  • SPI = 80,000 / 290,000 ≈ 0.28
  • CPI = 80,000 / 240,000 ≈ 0.33

The values indicate the project is both delayed and over budget, requiring corrective actions.

Conclusion

Performance metrics like SV, CV, SPI, CPI, and CSI are invaluable tools in project management for evaluating current project status, predicting future performance, and guiding corrective measures. Accurate calculation and interpretation of these indicators enable project managers to maintain control, optimize resource utilization, and enhance the likelihood of project success. Each scenario examined illustrates different performance states, highlighting the importance of continuous monitoring and adaptive management strategies.

References

  • Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Wiley.
  • PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) Sixth Edition. Project Management Institute.
  • Meredith, J. R., & Mantel Jr, S. J. (2014). Project Management: A Managerial Approach. Wiley.
  • Schwalbe, K. (2015). Information Technology Project Management. Cengage Learning.
  • Wysocki, R. K. (2014). Effective Project Management: Traditional, Agile, Extreme. Wiley.
  • Fleming, Q. W., & Koppelman, J. M. (2016). Earned Value Project Management. Project Management Institute.
  • Leach, L. P. (1999). Critical Chain Project Management. Artech House.
  • Heldman, K. (2018). PMP Project Management Professional Exam Study Guide. Sybex.
  • Heldman, K. (2018). PMP Exam Prep. Wiley.
  • Kloppenborg, T. J., Anantatmula, V., & Wells, K. (2019). Contemporary Project Management. Cengage Learning.