Developing A Project Plan
Developing A Project Plan 195idlegenddureslseflfsla1formp
Manage a product upgrade project for Bangkokagogo. Complete forward and backward passes on the project network, compute activity slack, identify the critical path, and create a Gantt chart showing slack for noncritical activities.
Sample Paper For Above instruction
Introduction
Project management involves meticulous planning, scheduling, and control of project activities to ensure successful completion within the designated timeframe and budget. Critical Path Method (CPM) and Gantt charts are essential tools used in this context for visualization and timeline management. This paper demonstrates the application of these tools in managing a product upgrade project for Bangkokagogo, focusing on forward and backward pass calculations, slack determination, critical path identification, and Gantt chart creation.
Project Network and Activities
The project network involves multiple activities, each with specific durations, dependencies, and sequencing. The activities include forming the project team, interviewing users, surveying users, identifying new features, acquiring materials, developing marketing campaigns, producing prototypes, designing graphics, conducting marketing, and performing sales calls.
| Activity | Description | Duration (days) | Dependencies |
|----------|---------------|-----------------|--------------|
| A | Form project team | 5 | - |
| B | Interview users | 3 | A |
| C | Survey users | 2 | A |
| D | Identify new features | 3 | B, C |
| E | Conduct marketing description | 4 | D |
| F | Acquire materials | 2 | D |
| G | Produce prototypes | 3 | D |
| H | Design graphics | 3 | G |
| I | Conduct marketing | 5 | E, H |
| J | Perform sales calls | 3 | I |
Forward Pass Calculation
The forward pass identifies early start (ES) and early finish (EF) times for each activity, starting from the project start date (day 0). The initial activity, forming the project team (A), begins at day 0 with an EF of 5 days.
Subsequent activities' ES are set as the maximum EF of their predecessors:
- B and C begin after A: ES=5, EF=8 for B; EF=7 for C.
- D begins after B and C: ES = max(8,7)=8, EF=11.
- F, G, E begin after D: F begins at 8, EF=10; G begins at 8, EF=11; E begins at 11, EF=15.
- H, which depends on G, begins at 11, EF=14.
- I depends on E and H: ES=15, EF=20.
- J depends on I: ES=20, EF=23.
Backward Pass Calculation
Backward pass starts from the project's completion time, which is the EF of the last activity (J), 23 days. The latest finish (LF) for activity J is 23 days, and the latest start (LS) is LF - duration = 20 days.
Working backward:
- I can finish by day 20, so LS=20, LF=20, and activities depending on I (J) have LF=20.
- E and H should finish by day 15 and 14, respectively; their LS are LF - duration.
- For activities with multiple successors, the LF is the minimum LS of their successors.
These calculations establish the latest start and finish times, revealing activities on the critical path.
Slack and Critical Path Identification
Slack (float) for each activity is calculated as LS - ES or LF - EF:
- Activities with zero slack are on the critical path.
- Activities with positive slack have flexibility in scheduling.
From calculations:
- Activities A, B, D, G, and I have zero slack; they form the critical path: A -> B -> D -> G -> I -> J.
- Activities like C, E, F, H, and others have positive slack values, indicating flexibility.
Gantt Chart Creation
A Gantt chart visually represents activity durations, dependencies, and slack:
- Critical path activities are shown as continuous bars without slack.
- Noncritical activities are shown with slack time, allowing buffer periods in the schedule.
The Gantt chart assists project managers in visualizing the schedule, identifying potential delays, and managing resources effectively.
Conclusion
Effective project management requires integrating network analysis, slack calculation, and visualization tools like Gantt charts. The detailed analysis of the Bangkokagogo product upgrade project demonstrates how forward and backward passes facilitate accurate scheduling, highlight critical activities, and help in allocating resources efficiently. Incorporating these methods enhances project control, minimizes delays, and ensures timely project completion.
References
- Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Wiley.
- Larson, E., & Gray, C. (2018). Project Management: The Managerial Process. McGraw-Hill Education.
- PMI. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). Project Management Institute.
- Schwalbe, K. (2015). Information Technology Project Management. Cengage Learning.
- Milosevic, D. Z., & Tummala, R. R. (2011). Evolving Role of Project Management in Engineering and Construction. Elsevier.
- Heldman, K. (2018). Project Management JumpStart. Wiley.
- Meredith, J. R., & Mantel, S. J. (2014). Project Management: A Managerial Approach. Wiley.
- Wysocki, R. K. (2014). Effective Project Management: Traditional, Agile, Extreme. Wiley.
- Gray, C. F., & Larson, E. W. (2020). Project Management: The Managerial Process. McGraw-Hill Education.
- Leach, L. P. (2014). Critical Chain Project Management. Artech House.