Earned Value Measurement: What Is It Represented By?
Earned Value Measurement Earned Value Is Represented By A
Identify and analyze key concepts and calculations associated with Earned Value Management (EVM), including the definitions of terms such as BCWS, BCWP, ACWP, and related variances and indices. Resolve specific project management scenarios using formulae for schedule and cost performance measurement, as well as understanding project baseline components and reporting formats.
Sample Paper For Above instruction
Earned Value Management (EVM) is a project management technique used to measure project performance and progress quantitatively. EVM integrates scope, schedule, and cost elements, enabling project managers to assess project health through specific metrics. Central to EVM are certain key performance indicators such as Budgeted Cost of Work Scheduled (BCWS), Budgeted Cost of Work Performed (BCWP), and Actual Cost of Work Performed (ACWP), each serving distinct roles in evaluating project status.
At the core, BCWS, also known as Planned Value (PV), represents the budgeted cost assigned to scheduled work up to a specific point in time. BCWP, or Earned Value (EV), indicates the value of work actually performed, measured in terms of the original budget. ACWP, or Actual Cost (AC), is the real expenditure incurred for the work performed. The relationship among these metrics allows for the calculation of variances and performance indices, which in turn support project control and forecasting.
The project status can be derived by analyzing these metrics. For instance, if BCWP exceeds BCWS, the project is ahead of schedule; conversely, if BCWP is less than BCWS, it indicates a delay. Similarly, comparing BCWP to ACWP reveals whether a project is under or over budget. Holding this analysis in context with baseline data, such as the Budget at Completion (BAC), enhances understanding of overall project health and future forecast predictions.
For example, when the BAC is $20,000 and the project is 40% complete, the earned value (BCWP) would be 40% of BAC, which equals $8,000. If the BCWS value (planned value at this point) is less than the BCWP, the project is ahead of schedule, whereas if the ACWP exceeds the BCWP, the project is over budget. These calculations aid in making informed decisions about project adjustments.
Project managers also rely on Cost Performance Index (CPI) and Schedule Performance Index (SPI) to assess cost-efficiency and schedule adherence respectively. A CPI greater than 1 indicates under-spending relative to the work performed, while an SPI less than 1 suggests that the project is behind schedule.
Furthermore, comprehensive reports such as performance reports, status reports, and forecast reports utilize these metrics to communicate project status effectively. The document that defines work packages, assigns charges, and establishes control points is typically referred to as the work authorization or code of accounts, establishing accountability for costs and schedule management.
In project management, unforeseen issues like escalation factors require contingency planning. Management reserves are budgets set aside to address such uncertainties without impacting the project's baseline. These are separately controlled and included as part of the overall project budgeting process.
Forecasting the project completion, including estimating the Estimate at Completion (EAC), Estimate to Complete (ETC), and variances, is critical for project control, with these figures appearing primarily in performance and forecast reports. For instance, if the BAC is known and CPI is over 1, the project’s forecasted cost at completion can be adjusted downward accordingly.
Application of the 50-50 rule assists in calculating earned value when progress measurement is challenging. This rule assumes that 50% of the remaining work, after an event or at specific points, is earned at a given time. This approach aids in calculating BCWP for projects with partial or uncertain progress data.
Analyzing project completion involves verifying that the total planned work and cost align with actual performance. Ideally, at project conclusion, the total Actual Cost (AC) should approximate the BCWP, and the Variance (SV) should be zero, indicating the project is completed as planned.
In cases of negative CV (Cost Variance), especially when comparing CV dollar amounts across months, percentage calculations help in understanding the trend and severity of delays or cost overruns. This segmented analysis helps determine whether the situation is improving or deteriorating over time.
To manage scope changes, project managers typically utilize customer-funded scope change processes and control budgets appropriately. Other sources of funding, such as management reserves, are kept for unpredictable risks, not specific scope modifications.
Adjusting project schedules based on performance indices is essential. For example, if CPI is 1.25, the project will likely finish earlier than initially planned; thus, the new scheduled completion date can be calculated by dividing the original duration by CPI, assuming consistent performance.
The baseline of project costs comprises the sum of planned budgets for different work packages, including the distributed and undistributed budgets, while management reserves and profit are set aside separately for managing risks and profit margins.
References
- PMI (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 6th Edition. Project Management Institute.
- Christie, C. (2015). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Wiley.
- Kloppenborg, T. J. (2019). Contemporary Project Management. Cengage Learning.
- Langer, S., & McGowan, R. (2018). Effective Project Management: Traditional, Agile, Extreme. J. Ross Publishing.
- Burke, R. (2013). Project Management: Planning and Control Techniques (5th Edition). Wiley.
- Merrow, E. (2011). Understanding Program Management. John Wiley & Sons.
- Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Wiley.
- Standish Group. (2015). CHAOS Report: The State of the Art in Project Management.