INF 410 Week 4 Assignment: Assume You Are The Project Manage

Inf 410 Week 4 Assign Onassume You Are The Project Manager For A Softw

Inf 410 Week 4 Assign Onassume You Are The Project Manager For A Softw

Assume you are the project manager for a software company and your team is in charge of delivering an update to tax preparation software for the next tax season. The project team has ten software developers working together, but located across the country. You have the following information about the project, and need to provide a status to the sponsors.

New items you learned this month about the project include: There is a three-day weekend in the coming month; nine of the developers are on track to finish their tasks two weeks early; one software developer took the recently announced “early retirement” package and is leaving in one week, confident he can complete his work before departure; hurricane season is active in Florida, where three developers are based; the developer retiring is the only person who knows how to get approval for the final product from the IRS; project costs are under budget and no overtime has been necessary.

Paper For Above instruction

The current status of the software update project aimed at preparing the tax software for the upcoming season is generally favorable, with key positive indicators suggesting we are on or ahead of schedule, and within budget constraints. The project team, composed of ten developers spread across the country, has demonstrated remarkable productivity, with nine of the ten expected to complete their respective tasks two weeks early. This ahead-of-schedule progress indicates the project is in a healthy state and moving towards its milestones efficiently. However, despite this positive outlook, there are two primary risks that could potentially impact the project's successful completion if not properly mitigated.

The first significant risk concerns the departure of the developer who has taken early retirement. This individual possesses unique knowledge, specifically the expertise to secure IRS approval for the final product. Losing this critical skill poses a substantial threat to timely project closure. To mitigate this risk, it is advisable to implement a knowledge transfer plan immediately, involving the retiring developer sharing critical information and procedures with remaining team members or new hires. Additionally, engaging a temporary consultant or bringing in a developer familiar with IRS approval processes could serve as a contingency plan to minimize delays.

The second major risk pertains to the hurricane season in Florida, where three team members are based. Severe weather could disrupt communication, delay work, or cause power outages, thereby affecting project timelines. To address this, the project manager should establish flexible work arrangements, such as remote work capabilities and backup communication channels, ensuring that the team can continue their tasks uninterrupted in case of weather disruptions. Monitoring weather forecasts closely and creating contingency plans for potential team member evacuations or outages will further mitigate this risk.

Overall, the project is currently rated as green, indicating healthy progress. Nonetheless, proactive risk management is essential to ensure continued success. It is recommended that the project team maintains transparent communication about potential issues and regularly updates contingency plans as new information arises. Given the early completion of most tasks and the project still being under budget, there are no immediate needs for additional resources. However, should weather disruptions or knowledge transfer challenges escalate, additional resources such as temporary consultants or backup infrastructure might become necessary.

Conclusion and Resource Requests

To safeguard against the identified risks, I recommend immediate implementation of knowledge transfer sessions with the retiring developer and enhancement of disaster recovery protocols for hurricane-related disruptions. Currently, no extra resources are required, but preparedness measures will help maintain project momentum. If weather forecasts predict severe storms, or if the knowledge transfer process encounters delays, additional personnel or technological support may be requested to stay on track and meet the project deadline.

References

  • Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. John Wiley & Sons.
  • Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). Sixth Edition. PMI.
  • Schwalbe, K. (2018). Information Technology Project Management. Cengage Learning.
  • Fisher, R., & Ury, W. (2011). Getting to Yes: Negotiating Agreement Without Giving In. Penguin Books.
  • Larson, E., & Gray, C. (2018). Project Management: The Managerial Process. McGraw-Hill Education.
  • Snyder, L. V. (2016). The Practice of Project Management. Wiley.
  • Heldman, K. (2018). PMP Project Management Professional Exam Study Guide. Sybex.
  • Leach, L. P. (2014). Critical Chain Project Management. Artech House.
  • Williams, T. (2017). Assessing and Managing Risks for Projects. Routledge.
  • AMP Incorporated. (2020). Disaster Preparedness and Business Continuity Planning. Technical Report.