Part 1: Project Schedules
You are assigned the task of creating a project schedule for implementing a new accounting system at your office. Since this is your first time doing so, you ask Antonio, a more experienced co-worker, for assistance. Antonio advises you that the best way to make sure that the project stays on schedule is to automatically add lead and lag to every activity.
Do you agree with Antonio’s advice? Why or why not? When might adding lead and lag be effective in project scheduling? When might it be ineffective? Write at least 200 words and support your answer with at least one additional professional or academic source.
Part 2: Emergency Call Box Project – Part 3: Schedule
Last week, you worked with your team to identify the tasks associated with installing several emergency call boxes on a 100-acre college campus.
Refer to the WBS that you created last week and complete the following:
- Identify the task dependencies.
- Assign dates and durations to each task and subtask.
- Assign human resources to each task and subtask.
- Create a Gantt chart illustrating the project tasks. Charts and diagrams must be created in MS Project. For assistance with MS Project, refer to Appendix A in your textbook.
Paper For Above instruction
The development of effective project schedules is paramount for the successful completion of any project. A pertinent aspect of this scheduling process involves understanding and correctly applying concepts such as lead and lag. Antonio’s advice to automatically add lead and lag to every activity merits careful consideration as its implications can significantly influence project timelines and resource management. This paper evaluates the appropriateness of such a blanket approach, explores scenarios where lead and lag are beneficial or detrimental, and applies these insights within the context of implementing a new accounting system.
Lead and lag are critical tools in project management used within the critical path method (CPM) to optimize scheduling flexibility. Lead refers to the overlap of activities, allowing subsequent tasks to commence before the previous tasks are fully completed. Conversely, lag introduces a delay between tasks, establishing a waiting period to allow resources or conditions to mature before moving forward. According to Meredith and Mantel (2017), precise application of these techniques can reduce project duration or enhance schedule realism, but indiscriminate use can lead to resource conflicts or scheduling inaccuracies.
Automatically adding lead and lag to every activity, as advised by Antonio, presumes that such adjustments inherently improve the project timeline. However, this blanket approach overlooks the nuances of task dependencies and resource constraints. Not all tasks benefit from overlaps; for instance, sequential or resource-dependent activities may be disrupted by unwarranted overlaps, leading to potential rework or resource contention. For example, in implementing a new accounting system, tasks such as data migration and staff training may require precise sequencing, where overlaps could cause confusion or errors (PMI, 2017).
Effective use of lead and lag is context-dependent. Lead is beneficial when activities can proceed concurrently without compromising quality, such as in early-stage planning or administrative preparations. Lag is useful in situations requiring physical or procedural delays, like waiting for hardware to arrive before installation or allowing a server to propagate updates. For example, when scheduling a project involving software testing, introducing a lag after coding ensures thorough review before testing begins, reducing the risk of oversight (Kerzner, 2013).
On the other hand, indiscriminate application of lead and lag can be ineffective or harmful. Overlapping tasks that are not truly independent may cause rework, delays, or increased costs. For instance, if data validation is overlapped with data migration unnecessarily, incomplete or incorrect data could compromise the system's integrity. Moreover, excessive lag could unnecessarily elongate the project timeline, wasting resources and delaying deliverables.
In conclusion, while lead and lag are invaluable tools in refining project schedules, their use should be judicious and tailored to the specific context of each activity. Automatic application of these techniques to all tasks is not advisable without a thorough task dependency analysis. Understanding when and how to utilize lead and lag ensures a balance between schedule efficiency and project quality, which is crucial in complex projects such as implementing new accounting systems.
Furthermore, the second part of the assignment emphasizes practical application using project management tools like MS Project. Assigning task dependencies, dates, durations, resources, and creating Gantt charts are vital steps toward a comprehensive project plan. These activities facilitate visualization, tracking, and adjustment, ensuring that the project adheres to its schedule and resource allocations. Integrating theoretical understanding with practical tools enhances overall project management efficacy.
References
- Kerzner, H. (2013). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Wiley.
- Meredith, J. R., & Mantel, S. J. (2017). Project Management: A Managerial Approach. Wiley.
- PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Project Management Institute.
- Fleming, Q. W., & Koppelman, J. M. (2015). Earned Value Project Management. Project Management Institute.
- Schwalbe, K. (2018). Information Technology Project Management. Cengage Learning.
- Wysocki, R. K. (2014). Effective Project Management: Traditional, Agile, Extreme. Wiley.
- Gido, J., & Clements, J. (2017). Successful Project Management. Cengage Learning.
- Nicholas, J. M., & Steyn, H. (2017). Project Management for Engineering, Business and Technology. Routledge.
- Heldman, K. (2018). Project Management JumpStart. Jossey-Bass.
- Heldman, K., & Baca, C. (2020). PMP Project Management Professional Exam Study Guide. Wiley.