Project Management Case You Are Working For A Large Apparel ✓ Solved

Project Management Caseyou Are Working For A Large Apparel Design And

Identify the core assignment question/prompt: Develop a comprehensive project plan to move the District 4 warehouse of Trillo Apparel Company (TAC), including scheduling, resource allocation, and risk management, ensuring completion within four months while minimizing production disruption.

Cleaned instructions: Create a detailed project management plan for relocating TAC's District 4 warehouse over four months. The plan should include scheduling activities, resource allocation, contractor management, permitting processes, and risk mitigation strategies to ensure minimal disruption to production and timely completion.

Sample Paper For Above instruction

Introduction

The relocation of a major production facility presents substantial logistical, operational, and strategic challenges, especially when aiming to minimize downtime and maximize efficiency. Trillo Apparel Company’s (TAC) District 4 warehouse move exemplifies such a complex project, requiring meticulous planning and execution. This paper develops a comprehensive project management plan to facilitate the seamless transfer of TAC's District 4 operations within a strict four-month timeline, ensuring minimal impact on production and revenue generation.

Project Overview

TAC's District 4 has outgrown its existing facility due to increased demand, necessitating a relocation 10 miles away to a new site with adequate space and infrastructure. The move involves multiple contractors and sequential construction phases, including permitting, framing, electrical, plumbing, drywall, and finishing. With a target completion date of four months, the project must also account for permitting delays, inspection schedules, and potential hazards that could elevate costs or cause schedule slippage.

Project Objectives

  • Complete the warehouse move within four months.
  • Minimize productivity disruption and prevent excessive downtime, not exceeding five days.
  • Ensure all construction and permits are completed according to city and county regulations.
  • Maintain a budget consistent with initial estimates of approximately $540,000 for construction activities.
  • Achieve operational readiness to generate additional $1 million annually in revenues by increasing production capacity.

Work Breakdown Structure and Scheduling

Effective scheduling hinges on defining logical sequential activities and proper resource assignment. The planning process involves constructing a Work Breakdown Structure (WBS) that includes permit acquisition, construction phases, equipment packing, and actual move activities. Critical path analysis reveals critical activities like permit approvals and framing, which could cause delays if not closely monitored.

The schedule begins with project initiation, including stakeholder meetings and documentation, followed by permit applications, expected to take 10 days for electrical, plumbing, and building permits. These activities are prerequisites for framing, which involves ordering supplies, framing, and inspections, scheduled over 15 days. Electrical and plumbing installations follow, each requiring 10 days, with inspections scheduled within the same window. Drywall installation and inspections are set for 15 and 10 days, respectively. Once all construction phases pass inspection, finishing, workbenches, and equipment packing are managed concurrently, with packing scheduled during last phases to ensure readiness for the move.

Resource Allocation and Contractor Management

To ensure timely progress, the project plan assigns responsibilities to specialized contractors: East Side Framing for framing, Sparks Electrical for electrical work, and Waterworks Plumbing for plumbing. Each contractor's schedule is aligned with their respective permit and inspection timelines, with contingencies factored in for possible delays.

Materials procurement, including drywall and electrical supplies, is scheduled prior to construction activities. The project plans to order supplies well in advance to prevent delays. Student workers are engaged for building workbenches, providing cost-effective labor during construction downtimes. Resource management emphasizes communication channels and accountability to detect and address issues early.

Permitting and Inspection Strategy

Permitting is critical to maintaining schedule integrity. The plan includes overlapping permit applications (electrical, plumbing, building) to expedite processing. Regular follow-ups with city and county inspectors are established, and backup plans involve engaging with flexible inspectors or applying for temporary permits, if available. Clear documentation and early application reduce the risk of inspections extending beyond scheduled windows, which would otherwise delay subsequent activities.

Risk Management and Contingency Planning

Projected risks include permit delays, contractor scheduling conflicts, unforeseen site conditions, and adverse weather. To mitigate these, the project schedule incorporates buffer periods after permit submission, and multiple bids are considered where possible. Cross-training staff and pre-placing equipment and materials facilitate rapid response to schedule overruns. Weekly status meetings ensure issues are identified early, and corrective actions are implemented promptly.

Cost Management

Budget adherence is maintained through detailed cost estimates, with expenditures closely monitored against contractual commitments. Contingency funds are allocated for emergencies such as additional inspections or repair requirements, estimated at 10% of project costs. Regular financial reviews enable corrective actions before budget overruns occur.

Conclusion

Executing this project requires disciplined scheduling, proactive resource management, and robust risk mitigation to ensure completion within four months with minimal operational disruption. The plan emphasizes early permitting, coordinated contractor activities, and continuous stakeholder communication, which are critical for success. By adhering to this comprehensive project management framework, TAC can realize the relocated warehouse’s benefits—enhanced capacity, increased revenue potential, and sustained profitability.

References

  • Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 6th Edition. PMI.
  • Kerzner, H. (2013). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 11th ed. Wiley.
  • Schwalbe, K. (2018). Information Technology Project Management. 9th Edition. Cengage Learning.
  • Heldman, K. (2018). Project Management JumpStart. 3rd Edition. Wiley.
  • Larson, E. W., & Larson, R. (2015). Project Management: The Managerial Process. 6th Edition. McGraw-Hill Education.
  • Milosevic, D., & Mihić, M. (2020). Construction Project Management. International Journal of Construction Management, 20(7), 680-691.
  • Olomolaiye, P., Harris, F., & Ng, C. (2012). Engineering and Construction Contracting. Wiley-Blackwell.
  • Too, E. G., & Weaver, P. (2014). Managing Sustainability in the Construction Industry. Journal of Construction Engineering and Management, 140(1), 04013041.
  • Flyvbjerg, B. (2017). The Oxford Handbook of Megaproject Management. Oxford University Press.
  • Gido, J., & Clements, J. (2014). Successful Project Management. Cengage Learning.