Utilizing the step-by-step MRP calculation process, students will develop a comprehensive understanding of material requirements planning by analyzing a detailed product structure and planning schedule based on given demand and lead times.

The assignment requires students to first construct a bill of materials (product structure tree) for a product system, then generate an MRP schedule to meet a specified demand at a future time point, considering lead times and zero initial inventory.

Specifically, students will need to:

  • Construct and interpret the product structure tree illustrating how end products are assembled from subcomponents.
  • Calculate gross requirements for each item based on end-item demand and BOM structure.
  • Assess net requirements after considering on-hand inventory (initially none).
  • Calculate the planned order releases considering lead times and demand timing.
  • Develop a detailed weekly schedule for ordering and receiving components to fulfill the demand of 100 units of product A in week 10.

Paper For Above instruction

Material Requirements Planning (MRP) is a crucial manufacturing process that ensures the timely procurement and production of components necessary for final product assembly. As an essential part of supply chain management and production planning, understanding the step-by-step calculation method equips students with the ability to schedule production and inventory efficiently, reducing costs and improving responsiveness to customer demands.

The focus of this paper is to elucidate the step-by-step process involved in executing MRP calculations, particularly through constructing the product structure tree and developing a detailed schedule based on specified demand signals, lead times, and inventory statuses. This process is fundamental for manufacturing managers, production planners, and supply chain analysts aiming to optimize resource allocation and meet customer delivery commitments.

Constructing the Product Structure Tree (Bill of Materials)

The initial step involves translating the product architecture into a visual product structure tree or BOM (Bill of Materials), which describes how the final product is assembled from various components at different levels. For the scenario provided, the end item is Product A, assembled from components B and C in a ratio of 2:4, respectively.

Furthermore, B itself is assembled from D and E in a ratio of 3:2, and C is assembled from F and E in a ratio of 2:2. A simplified graphical representation illustrates this hierarchy:

  • Product A: assembled from 2 units of B and 4 units of C
  • B: assembled from 3 units of D and 2 units of E
  • C: assembled from 2 units of F and 2 units of E

This structure indicates each component’s dependency on subcomponents, which must be scheduled and ordered considering their respective lead times.

Calculating the Material Requirements and Schedule

The primary goal is to fulfill a demand of 100 units of Product A in week 10, with no initial inventory on hand. The process involves calculating gross requirements for all components based on the product structure, then adjusting these with net requirements after accounting for on-hand stock.

Step 1: Determine total gross requirements for Product A in week 10: 100 units.

Step 2: Calculate requirements for each subcomponent based on the BOM structure. For each Product A unit, the requirements for B and C are scaled accordingly:

  • B: 2 units per A, so 200 units needed in week 10 for 100 units of A.
  • C: 4 units per A, so 400 units needed in week 10.

Step 3: Break down B and C into their respective components, considering their specific requirements:

  • D: Required for B, which is 3 units per B. For 200 B units, total D needed = 200 * 3 = 600 units.
  • E: E is used in both B and C:
    • In B: 2 units per B → 200 * 2 = 400 units
    • In C: 2 units per C → 400 * 2 = 800 units

    Total E requirements = 400 + 800 = 1,200 units in week 10.

  • F: Only used in C, 2 units per C, thus 400 * 2 = 800 units needed in week 10.

Scheduling Based on Lead Times

Lead times affect when each order should be placed to ensure materials arrive just in time for assembly. For the components, the specified lead times are as follows:

  • Product A: 1 week
  • B, C, E: 2 weeks
  • D, F: 3 weeks

Given these lead times, the planned order release weeks are calculated in reverse from the demand week:

  • Product A: demand in week 10, start planning for orders in week 9 (lead time of 1 week).
  • B, C, E: require arrival by week 8 (since demand is week 10), so orders for these components need to be released in week 6 (due to 2-week lead time).
  • D and F: require arrival by week 7 for week 10 assembly, so orders should be placed in week 4 (due to 3-week lead time).

Creating the MRP Schedule

The schedule systematically specifies when orders are placed and received for each component based on the above calculations:

  • Week 4:
    • Order D: 600 units (for B requirement)
    • Order F: 800 units (for C requirement)
  • Week 6:
    • Order B: 200 units (for final assembly in week 9)
    • Order C: 400 units
    • Order E: 1,200 units (sum of requirements for B and C)
  • Week 9:
    • Order A: 100 units to meet demand in week 10 (considering 1-week lead time)

This schedule ensures all components arrive just in time for assembly, optimizing inventory levels and reducing excess stockholding costs.

Conclusion

The step-by-step MRP process exemplifies how detailed analysis of product structure, demand signals, and lead times can support effective manufacturing planning. The accurate construction of the bill of materials and diligent calculation of net requirements enable companies to synchronize procurement and production activities, ultimately fulfilling customer demands efficiently. Mastery of this process is essential for manufacturing managers aiming to enhance operational performance and maintain competitive advantage in dynamic markets.

References

  • Harper, P. (2010). Production & Operations Management. McGraw-Hill Education.
  • Heizer, J., Render, B., & Munson, C. (2020). Operations Management. Pearson Education.
  • Jacobs, F. R., & Chase, R. B. (2018). Operations and Supply Chain Management. McGraw-Hill Education.
  • Vollmann, T. E., Berry, W. L., Whybark, D. C., & Jacobs, F. R. (2015). Manufacturing Planning and Control for Supply Chain Management. McGraw-Hill Education.
  • Stevenson, W. J. (2018). Operations Management. McGraw-Hill Education.
  • Slack, N., Brandon-Jones, A., & Burgess, N. (2019). Operations Management. Pearson Education.
  • Gunasekaran, A., & Ngai, E. W. T. (2004). Build-to-Order Manufacturing: Theories and Practices. International Journal of Production Economics, 74(1), 1-4.
  • Nahmias, S. (2013). Production and Operations Analysis. Waveland Press.
  • Shtub, A., & Karni, R. (2014). ERP: The Dynamics of Supply Chain and Manufacturing Management. Springer.
  • Chopra, S., & Meindl, P. (2016). Supply Chain Management: Strategy, Planning, and Operation. Pearson.