You Have Kicked Off The District 4 Production Warehouse Move Project

You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits. You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained. In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.

Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall. Your project plan should also be updated with the new 3-week timeline for obtaining permits. Use the project plan you created for this task. You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.

You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000. Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation. Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan. Submit both your updated project plan and PowerPoint presentation.

Paper For Above instruction

The successful completion of the District 4 Production Warehouse Move project hinges on effective project planning, risk management, and strategic decision-making. Given unforeseen delays in obtaining permits and constraints on contractor availability, project managers must adapt their schedules while maintaining the project timeline within the strict four-month deadline set by senior management. This paper discusses an updated project plan that incorporates these delays, explores options for schedule compression, and recommends an optimal solution to ensure project completion on time.

Updating the Project Schedule

Initially, the permit acquisition process was projected to take two weeks. However, delays have extended this to three weeks, necessitating an adjustment in the project timeline. To account for this, the project schedule will incorporate an additional week for permit procurement. Incorporating this delay ensures that subsequent project activities are correctly aligned with the new timeline.

Additionally, the framing and drywall contractors have experienced delays in their other ongoing projects, resulting in only half of their crews being available for this project. This situation effectively doubles the expected duration for framing and drywall installation work. To reflect this, the timelines for these activities should be doubled in the project schedule.

Adjusting these schedules will extend the project's duration beyond the original plan, risking a breach of the four-month completion window. Therefore, schedule compression techniques, such as fast-tracking or crashing, must be employed. Fast-tracking, which involves overlapping activities, can be utilized for non-dependent tasks. Crashing, which involves adding resources to critical tasks, may also be necessary but will increase costs.

Evaluating Schedule Compression Options

Fast-tracking can reduce the overall project duration by overlapping permitting and construction activities. For example, initiating framing work before permits are fully approved and obtained can save time. However, this approach carries risks related to rework if permits are delayed or conditions change.

Crashing, on the other hand, involves adding additional resources, such as hiring another contractor at an increased budget of $200,000, to accelerate framing and drywall work. This approach can significantly shorten the schedule but must be weighed against the increased costs and potential diminishing returns.

Proposed Solution

Given the need to stay within the four-month deadline and the increased costs associated with crashing, a hybrid approach is recommended. The project team will employ fast-tracking for some preliminary activities, such as starting framing on areas with permits in hand, while also employing crashing techniques—hiring additional contractors—to expedite critical activities. Specifically, the project will hire an additional contractor to help with framing and drywall, blending this with fast-tracking strategies to optimize schedule compression without excessive cost or risk.

This approach will increase the budget by $200,000 but will significantly reduce the project duration, bringing it within the required four-month window. The updated project plan will reflect these changes, including adjusted timelines, resource allocations, and milestones. The revised schedule will be documented using a Gantt chart to clearly illustrate overlapping activities and critical path adjustments.

Recommendations for Implementation

The project team should prioritize activities based on criticality and dependency, ensuring that the most time-sensitive tasks are fast-tracked or crashed first. Regular project monitoring and risk management will be essential throughout the implementation phase to address unforeseen issues promptly. Communication with stakeholders must emphasize transparency regarding schedule modifications and budget implications.

Furthermore, contractual arrangements with new contractors should include clauses for scope, quality, and schedule adherence to mitigate potential risks of delays or cost overruns.

By combining schedule compression techniques with strategic resource allocation, the project can meet its four-month deadline effectively, albeit with a higher budget. This solution aligns with senior management’s objectives and ensures the timely completion of the warehouse move, thereby supporting operational continuity and strategic goals.

Conclusion

In conclusion, the revised project plan reflects necessary schedule adjustments due to permit delays and contractor availability issues. Employing a combination of fast-tracking and crashing, specifically by hiring additional labor resources, provides a feasible path to completing the project within the four-month deadline. Effective monitoring, communication, and risk management will be critical to ensuring that the project remains on track and within budget, ultimately delivering a successful warehouse relocation.

References

  • Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling. John Wiley & Sons.
  • Meredith, J. R., & Mantel, S. J. (2014). Project management: A managerial approach. John Wiley & Sons.
  • PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Project Management Institute.
  • Harrison, F., & Lock, D. (2017). Advanced project management: A structured approach. Gower Publishing, Ltd.
  • Schwalbe, K. (2018). Information technology project management. Cengage Learning.
  • Gido, J., & Clements, J. (2017). Successful project management. Cengage Learning.
  • Heldman, K. (2018). Project management jumpstart. John Wiley & Sons.
  • Williams, T. (2018). The principles of project management. CRC Press.
  • Atkinson, R. (1999). Project management: Cost, time, and quality, two best guesses and a phenomenon, it's time to accept the trade-offs. International Journal of Project Management, 17(3), 181-192.
  • Turner, R., & Keegan, A. (2001). Management changes in the essence of projects. Long Range Planning, 34(1), 27-45.