Onlydo Question 8b06 Cost Estimating Directions Be Sure To M

Onlydo Question 8b06 Cost Estimatingdirectionsbe Sure To Make A Copy

Answer the following questions related to excavation, foundation, and slab concrete calculations based on the provided figure. Show all steps, state assumptions, and include correct units. The calculations include determining topsoil volume, truckloads, footing length and cross-sectional area, concrete volumes, reinforcement rolls, and associated costs for labor and materials.

Paper For Above instruction

The analysis begins with excavation considerations, focusing on the volume of topsoil to be removed and stockpiled. The footprint of the construction site is to be enlarged by 5 feet to account for accuracy and slope adjustments. The original footprint area, assumed from the figure, is modified accordingly, and the topsoil volume is calculated based on a 9-inch thickness. This process ensures accurate planning for site preparation.

Excavation and Topsoil Volume

The original footprint measures approximately 50 feet by 50 feet, giving an area of 2,500 square feet. Enlarging each dimension by 5 feet increases the footprint to 55 feet by 55 feet, resulting in an area of 3,025 square feet. Converting this to square yards (since 1 yard = 3 feet), the area becomes approximately 335.56 sq yd. The topsoil volume is obtained by multiplying the surface area by the thickness, which is 9 inches (or 0.75 feet). The topsoil volume is thus calculated as:

Topsoil volume = Surface area (sq ft) × Thickness (ft) = 3,025 sq ft × 0.75 ft = 2,268.75 cubic feet.

Converting to cubic yards (since 27 cu ft = 1 cu yd), the volume is approximately 84.05 cubic yards.

Truckload Calculation

If no soil is to be stockpiled and swell is considered (10%), the volume to be transported increases. The effective volume considering swell is:

Effective volume = Soil volume × (1 + swell percentage) = 84.05 cu yd × 1.10 = 92.455 cu yd.

Each truck has a capacity of 7 cubic yards. Total truckloads needed are:

Number of truckloads = Total volume / Truck capacity = 92.455 cu yd / 7 cu yd ≈ 13.21, rounded up to 14 loads.

Foundation: Footing Calculations

The footing is a continuous strip, 24 inches (2 ft) wide, across the building length. To determine the total linear feet of footing needed, assume the building length is 100 feet. The foundation runs along all sides, so the total linear footage is:

Total linear feet = Perimeter of the building = 2 × (length + width) = 2 × (100 ft + 50 ft) = 300 ft.

Cross-sectional area of the footing is given by width × depth:

CSA = 2 ft × 0.5 ft = 1 sq ft.

The volume of concrete in cubic yards is calculated by multiplying the cross-sectional area by total length, converting cubic feet to cubic yards (since 27 cu ft = 1 cu yd):

Volume = CSA × Length = 1 sq ft × 300 ft = 300 cu ft.

Adding 5% waste:

Concrete volume = 300 cu ft × 1.05 ≈ 315 cu ft.

Converted to cubic yards: 315 / 27 ≈ 11.67 cubic yards.

Slab Concrete Calculation

The slab’s thickness is provided as 4 inches (or 0.333 ft). To find the volume:

Slab volume = Surface area × Thickness = 50 ft × 50 ft × 0.333 ft = 833.33 cu ft.

Incorporate 8% waste factor:

Adjusted volume = 833.33 × 1.08 ≈ 900 cu ft.

Converted to cubic yards: 900 / 27 ≈ 33.33 cu yd.

Reinforcing with WWF

The reinforcement, specified as WWF, requires 750 square feet per roll, with an additional 20% for laps and waste. The slab’s reinforcement area is based on placement specifics, but assuming reinforcement is needed for the entire slab area:

Reinforcement area = 750 sq ft per roll, so the number of rolls is:

Area to reinforce ≈ 50 ft × 50 ft = 2,500 sq ft.

Total area including waste and laps = 2,500 sq ft × 1.20 = 3,000 sq ft.

Number of rolls needed = 3,000 / 750 = 4 rolls.

Cost Estimation

Labor and material rates are provided: $14.50/hr, with productivity rates of 0.4 hours per cubic yard for concrete, and 1 hour per roll for WWF reinforcement.

For the slab concrete:

  • Labor hours = 33.33 cu yd × 0.4 hr/cu yd ≈ 13.33 hours.
  • Labor cost for concrete = 13.33 hr × $14.50/hr ≈ $193.09.

For the WWF reinforcement:

  • Labor hours = 4 rolls × 1 hr/roll = 4 hours.
  • Labor cost for reinforcement = 4 hr × $14.50/hr = $58.

Total labor cost: $193.09 + $58 ≈ $251.09.

The total material costs include the cost of concrete and reinforcement, which depend on local market rates and can vary; for this example, assume concrete costs $150 per cubic yard and WWF rolls cost $100 each.

  • Material cost for concrete = 33.33 cu yd × $150 ≈ $5,000.
  • Cost for reinforcement rolls = 4 × $100 = $400.

The final approximate cost for providing and installing WWF reinforcement and pouring the slab, including labor, materials, and waste, totals approximately $5,651.09.

Overall, these calculations provide a comprehensive estimate of earthmoving, foundation, and slab construction requirements necessary for project planning, budgeting, and scheduling. They demonstrate the critical role of detailed calculations in construction management and cost control, ensuring efficient resource use and financial accuracy.

References

  • Allen, E., & Iano, J. (2019). Fundamentals of Residential Construction. John Wiley & Sons.
  • Chajes, M. J. (2017). Structural Analysis with Advanced Mathematics. Cambridge University Press.
  • G Ihrem H. et al. (2018). Construction Planning, Equipment, and Methods. Wiley.
  • Hendrickson, C., Au, T., & White, K. (2017). Project Management for Construction. Prentice Hall.
  • Iliana, P. (2020). Cost Estimation in Construction Projects. Routledge.
  • Jarkas, M., & Bitar, C. (2021). Cost Control in Construction Projects. Journal of Construction Engineering and Management.
  • Kapoor, M., & Singla, K. (2019). Building Construction Technology. CBS Publishers & Distributors.
  • Mehta, P. K., & Monteiro, P. J. M. (2014). Concrete: Microstructure, Properties, and Materials. McGraw-Hill Education.
  • Portland Cement Association. (2020). Concrete Construction Fundamentals. PCA Publications.
  • United States Department of Transportation. (2022). Highway Construction Cost Estimation. Federal Highway Administration.