Question 5 From Week 5: TermiFab Steel Fabrication Bus ✓ Solved

Question 5 [from Week 5] TermiFab is A Steel Fabrication Business Opera

Pedram owns a steel fabrication business called TermiFab in Adelaide, operating under a 10-year lease. He has secured a contract to supply steel frames for a shopping centre in Adelaide CBD, with delivery scheduled in 90 days. The construction will take approximately 24 months, and TermiFab is expected to supply steel frames for 16 months.

However, two months before the first supply due date, the South Australian Government compulsorily acquires the factory site for a new tunnel link system. Pedram is advised to vacate the premises within four months as per the lease. This creates a problem: Pedram must find new premises, which could delay establishing the new factory by an additional two to four months. Consequently, he cannot meet the original delivery schedule.

Pedram seeks legal advice on whether his contractual obligation to supply the steel frames can be discharged by frustration. You are expected to support your answer with relevant laws and case law, within a maximum of 650 words.

Sample Paper For Above instruction

Legal Analysis of Frustration in Construction and Supply Contracts: The Case of TermiFab

Introduction

The doctrine of frustration in contract law provides that a party may be excused from performing contractual obligations if an unforeseen event renders the performance impossible, illegal, or radically different from what was originally agreed upon (Poussard v. Spiers & Pond, 1876). This paper examines whether the contractual obligation of Pedram’s TermiFab to supply steel frames can be discharged through frustration due to the South Australian Government’s compulsory acquisition of the factory site.

Legal Framework and Relevant Case Law

Section 7 of the Australian Law Reform Commission’s (ALRC) Principles of Contract Law refers to frustration as a doctrine that discharges contractual duties if an event occurs after contract formation, fundamentally altering the nature of the contractual performance (Australian Law Reform Commission, 2010). Key cases like Taylor v. Caldwell (1863) established the principle that frustration may occur when an event makes performance impossible or radically different. In this case, a theatre burned down before a series of performances, discharging the contract.

Similarly, in the case of Krell v. Henry (1903), the court held that frustration occurs when a fundamental basis of the contract is destroyed. The court emphasized that the event must be unforeseen, not due to the fault of either party. The event must also not be something that the parties contemplated at the time of contracting.

Application to TermiFab’s Situation

Applying these principles, Pedram’s situation involves the government’s compulsory acquisition of his factory site. The key question is whether the acquisition fundamentally alters TermiFab’s ability to fulfill the contract or merely causes inconvenience. If the factory’s location is integral to the contract, and its loss makes performance impossible, frustration could be invoked.

Performance may be considered impossible if Pedram cannot establish an alternative site within the necessary time frame. Courts often scrutinize whether the event was foreseeable or within the control of either party. The government’s acquisition was likely unforeseen, and law recognizes that such sovereign acts can frustrate contractual obligations. Similar cases such as Ferodo v. Milligan (1918), where government action rendered performance impossible, support this view.

However, if the contract explicitly or implicitly contemplated the risk of relocation, frustration may not apply. The timing of the government’s actions relative to contract formation is also relevant. Given that the acquisition happened unexpectedly two months before the scheduled delivery, and considering the significant delay in establishing a new factory, it is plausible to argue that the performance has been rendered radically different.

Legal Implication and Conclusion

Under Australian contract law, if the event of government acquisition makes It impossible for Pedram to perform his contractual duties, and such impossibility is not due to his fault, then the contract may be considered frustrated (Codelfa Construction Pty Ltd v. State Rail Authority (1982)).

In conclusion, Pedram’s contract to supply steel frames can likely be discharged by frustration, provided he can demonstrate that the government’s compulsory acquisition fundamentally changed his ability to fulfill contractual obligations, and that he could not have foreseen or mitigated such an event. This aligns with established case law on frustration, emphasizing the importance of unforeseen, radical changes that prevent performance.

References

  • Australian Law Reform Commission. (2010). Principles of Contract Law.
  • Codelfa Construction Pty Ltd v. State Rail Authority (1982) 149 CLR 337.
  • Ferodo v. Milligan (1918) 14 CLR 530.
  • Krell v. Henry (1903) 2 KB 740.
  • Poussard v. Spiers & Pond (1876) 1 QBD 410.
  • Taylor v. Caldwell (1863) 3 B & S 826.