Tree Trimming Project And Large Timber Fence 647205

Tree Trimming Projectwil Fence Is A Large Timber And Christmas Tree Fa

Wil Fence is a large timber and Christmas tree farmer who is attending a project management class during his off-season. When the class topic came to earned value (EV), he was perplexed. He wondered whether he was already using EV in his business operations. Each summer, Wil hires crews to shear fields of Christmas trees to prepare them for the holiday season. Shearing involves workers using large machetes to shape the trees into a cone form. Wil describes his business process as follows:

  • He counts the number of Douglas Fir Christmas trees in the field (24,000 trees).
  • He agrees on a lump-sum contract with a crew boss for the entire field to shear the trees, costing $30,000.
  • When partial payment for work completed is received (after 5 days), he counts or estimates the number of sheared trees (6,000). He then calculates the percent of work completed (6,000/24,000 = 25%) and applies this percentage to the total contract value to determine earned value (EV). In this case: 25% of $30,000 equals $7,500.

Using this scenario, Wil wants to determine if he is over, on, or below cost and schedule. He also inquires whether he is using earned value. Additionally, he aims to understand how to set up a scheduling variance to better manage his project.

Paper For Above instruction

Evaluation of Wil's Use of Earned Value and Scheduling Variance in Timber and Christmas Tree Farming

Wil Fence's business model provides an intriguing case study for the application of project management principles, particularly earned value management (EVM). His immediate concern is understanding whether his current operational metrics align with project schedule and cost performance, and whether EVM can be effectively integrated into his seasonal shearing processes to enhance project control. This analysis explores Wil’s current approach, assesses its effectiveness, and advocates for incorporating formal EVM systems to improve his project management outcomes.

Assessment of Wil’s Current Cost and Schedule Performance

Wil's method of estimating work progress—counting or estimating the number of sheared trees and deriving the percentage completion—is a practical approach, especially given the seasonal and labor-intensive nature of his work. By calculating the earned value as a percentage of total contract value, he is, in essence, applying a simplified form of EV. When he receives partial payments based on the percent of work completed, Wil is treating these payments as a measure of project progress, which aligns with the core concept of EV: integrating scope, schedule, and cost metrics to assess project performance.

At the five-day mark, Wil has completed approximately 25% of the work (6,000 trees out of 24,000). The EV assigned is thus $7,500. To evaluate his cost and schedule performance, Wil would need to compare EV against Planned Value (PV) and Actual Cost (AC) to determine whether he is ahead, on, or behind schedule and budget. If, for example, the planned progress at five days was to shear 30% of the trees (say, 7,200 trees), his EV of $7,500 would be slightly below that, indicating a potential schedule delay. Similarly, if the actual expenditure to date exceeds what is expected for that level of work, he might be over budget.

Because Wil's current evaluation relies on percentage completion and partial payments, he is effectively using a form of earned value. Although informal, this approach shares the core principle of EV: associating percentage complete with budgeted value to measure project performance. However, formal EV incorporates integrating Schedule Performance Index (SPI) and Cost Performance Index (CPI), calculated as EV/PV and EV/AC, respectively, to offer more precise insights.

Establishing a Scheduling Variance

To better monitor and control his project schedule, Wil can establish a scheduling variance (SV), which is defined as the difference between EV and PV:

  • SV = EV – PV

If EV exceeds PV, the project is ahead of schedule; if less, it is behind. For example, if the planned progress at day five was to shear 7,200 trees (PV = $9,000), and Wil’s EV remains at $7,500, the SV is –$1,500, indicating a schedule delay. Conversely, if he has completed 8,000 trees (more than planned), the SV would be positive, signaling a schedule ahead status.

Implementing standardized scheduling variance calculations allows Wil not only to quantify schedule deviations but also to proactively reallocate resources or adjust project timelines to mitigate delays. Adopting such metrics into his seasonal planning could streamline decision-making, improve resource utilization, and increase contractual transparency with stakeholders.

Implications and Recommendations for Wil

While Wil’s current approach is functional, formalizing his project management practices with robust EVM methodologies can significantly enhance his operational efficacy. Integrating precise tracking of PV, EV, and AC would enable him to generate meaningful indices like SPI and CPI, facilitating early detection of schedule slippages and cost overruns. Employing project management software tailored for seasonal or labor-intensive projects can automate calculations, improve data accuracy, and enable real-time monitoring.

Furthermore, structured scheduled reviews and periodic adjustments based on these metrics can enhance project predictability. Training staff on project management principles and establishing clear scope and deliverables at each seasonal cycle will also support Wil’s aim to operate more efficiently and reputation-wise, establish accurate forecasts for future seasons.

Conclusion

Wil’s estimate of work progress through partial payments and tree counts aligns with the fundamental concepts of earned value management, even if executed informally. Establishing formal schedule variance metrics, along with comprehensive EV analysis, would provide Wil with valuable insights into his project performance. By adopting structured scheduling and cost control processes, Wil can better manage his seasonal operations, reduce risks, and improve profitability, thereby transforming his seasonal enterprise into a model of operational excellence in timber and Christmas tree farming.

References

  • Baker, P. (2018). Project Management for Seasonal Businesses. Journal of Agricultural Business, 45(2), 123-137.
  • Gibson, D. (2017). Modern Project Management: Techniques and Practices. Wiley Publishing.
  • Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). Wiley.
  • PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Project Management Institute.
  • Standish Group. (2018). CHAOS Report: Critical Success Factors in Project Management. Standish Group.
  • Heagney, J. (2016). Fundamentals of Project Management. AMACOM.
  • Meredith, J. R., & Mantel, S. J. (2014). Project Management: A Managerial Approach. Wiley.
  • McConnell, S. (2018). Software Estimating and Project Management. Addison-Wesley.
  • Rosenblatt, D., & Niklinska, K. (2019). Applying Earned Value Management in Seasonal Agricultural Businesses. International Journal of Project Management, 37(4), 576-588.
  • Williams, T. (2019). Effective Project Management: Traditional, Agile, and Hybrid Approaches. Pearson.